logo  
Change font size
 
Home | Contact | Sitemap
   

28.01.2011 General Assembly and Election of new Presidency
more

18.06.2010 General Assemly adopted Declaration to Develop Rail Traffic
more

21.04.2010 Report EU-Strategy for the Danube Region
more

01.07.2009 General Assembly Korridor X PLUS in Zagreb
more

09.04.2009 From Belgrade to Salzburg for € 39
more

18.03.2009 Successful Journey from Ljubljana to Istanbul/Halkali
more

"Korridor X PLUS" having been founded
more

AKX Progress Report
more

Our action programme
gives information about the current activities. more

Corridor X-Network Access Description
download. more

Meeting of the CEOs
of the railways of SEE in Brussels. more

High-ranking meeting
of ARGE Korridor X in Vienna. more

Market Project 7
Cutting Stops in Border Stations

Objective: Shortest possible stops in border stations

Tasks:

  • Analysis about reasons for stops (use existing studies!)
  • Define measures for reduction of stops
  • Clarify potential for short and mid term reduction together with parties involved
  • Co-ordination with state authorities absolutely necessary

Project leader: Serbian Railways (Zeleznice Srbije ZS)

Status:

  • Analysis about reasons for stops (using existing studies! – e.g. UIC-study) – in process
  • Definition of measures for reduction of stops – in process
  • Clarification of potential for short and mid term reduction together with parties involved
  • Co-ordination with state authorities absolutely necessary

Start: January 2006

End: 1st milestone in June 2006

   